What is an NOC?
Legal notice to the
county's register of deeds that remodeling/improvements will be
undertaken at an address.
All mechanics'
liens relate back to the date the notice of commencement was
recorded, thus enabling the construction mortgage to remain a first
lien, not subordinated to any labor or supplier claim for nonpayment
of bills.
What is a Notice to
Owner?
Florida
law requires that anyone who supplies labor, services or material to
a contractor on any construction job must send the
owner of the construction project a 'Notice to Owner' form to
protect their rights to getting paid on the construction project.
The Notice to Owner is not a lien on property. It DOES NOT mean that
a contractor has failed to pay the company who has given the notice.
It merely informs the recipient that the company identified in the
Notice to Owner is on a specific job and provides a general
description of the type of materials they are supplying or the type
of work that they will be performing.
Before paying a
contractor, the property owner must make sure that the person who
has given the Notice to Owner has been paid by the contractor. This
is done by getting a lien waiver from the person identified in the
Notice to Owner (Lienor's name and address). If a construction
lender is paying the contractor directly, the lender is responsible
for getting the necessary lien waivers. The property owner should
check with the lender to verify that they will be managing these
documents in connection with each payment to the contractor.
However, it is ultimately the property owners responsibility to make
sure that the correct lien waivers are received from all parties on
the project and that all who have supplied labor, services or
material on the job have been paid. If there is no lender involved,
the Contractor should provide a “Partial Release of Lien” from the
supplier. Once the supper is 100% complete, then you should receive
a “Final Release of Lien” from the supplier. All releases, whether
Final or Partial, should be notarized.
How
do you handle allowances?
The description of
all specific items to be included in the Addition for which Owner
has a choice and the allowances for such specific items are included
in the Construction Documents. If Owner exceeds the dollar amounts
for allowance set for each item, Owner agrees to execute a written
Change Order or an addendum to this Agreement whereby Owner agrees
to pay such excess in cash upon Contractor’s direction at any time
and from time to time during construction. If Owner does not spend
the allowance limit, Contractor will adjust the reduction at payment
# 6. Contractor
will provide Owner a general estimate of selections made under
Allowances. These are estimates and actual charges will be billed to
Owner through an Allowance schedule with copies of invoices
provided. For all cost
items based on an Allowance, Contractor shall charge Owner the
actual cost as charged by the supplier, plus 15% markup for
Contractor on all overages to the Allowance amount.
All monies not spent for an Allowance Item will be a net
credit of the difference of monies spent verses the actual allowance
figure for that item.